ELECTRICAL SYSTEMS - GENERATORS
POWER GENERATION
Generators play an important part in your assignment with the Seabees. Whether operating a generator as a main power source or as standby power or as emergency power, you need a through knowledge of their hookup, operation, and maintenance. At the completion of this chapter, you should know how to install generators of the advanced-base type, stand a generator watch, perform preventive maintenance, and make minor repairs on power generators and control equipment. Theory for both dc and ac generators is included in Navy Electricity and Electronics Training Series (NEETS), Module 5. Generator theory will not be covered in this chapter. Keep in mind that the generator (alternator) in an automobile works on the same principle as does the huge turbine generator used in a nuclear power station.
INSTALLATION AND SERVICING
GENERATORS
Most of the generators you are likely to work with in the Naval
Construction Force (NCF) range in size from 5 kW to 200 kW. Generators in these
sizes range in weight from 488 pounds (221.4 kg) to 10,500 pounds (4770 kg).
All of these units are mounted on skid bases. Lifting and tie-own attachments
are provided. All have provisions for lifting with a forklift of the appropriate
capacity (with the exception of the 5-kW gas-driven generator set, which does
not include the forklift provision). Several factors should be considered before
a final decision is made about where to locate a generator. The noise levels
of generators sized from 5 kW to 200 kW range from 77 dBa to 93 dBa (adjusted
decibels) at 25 feet. Generator noise is a problem in low-noise level or quiet
areas (libraries, offices, hospitals, chapels, etc.).
The operating 60-kW generator, for example, presents a noise hazard (84 dBa to 91 dBa, depending on the model) to all personnel in the immediate area. The noise level near the unit exceeds the allowable limits for unprotected personnel. Therefore, everyone working around the generator needs single (noise < 84 dBa) or double hearing protection (noise > 104 dBa).
Placing a generator set near points of large demand will reduce the size of wire required, hold the line losses to a minimum, and afford adequate voltage control at the remote ends of the lines.
The following points should be considered before an exact site is chosen for a generator set:
1. Generators must not be
closer than 25 feet (7.6 meters) to a load because of noise, fire hazard, and
air circulation.
2. The set must be placed on a stable, preferably level, foundation. It should
not be operated while inclined more than 15 degrees from level.
3. The site must be within 25 feet (7.6 meters) of any paralleled generator
set and within 25 feet (7.6 meters) of any auxiliary fuel supply.
4. When preparing a temporary installation, you should move the generator set
as close to the jobsite as practical. In an area where the ground is soft, do
not remove the wood-skid base if you have not already done so. The wood-skid
base will establish a firm foundation on soft ground, mud, or snow; otherwise,
use planks, logs, or other material for a base in an area where the ground is
soft.
Although advanced-base portable generators are designed to be operated outdoors, prolonged exposure to wind, rain, and other adverse conditions will definitely shorten their lives. When the generators are to remain on the site for any extended period of time, they should be mounted on solid-concrete foundations and should be installed under some type of shelter.
There are no predrawn plans for shelters for a small advanced-base generating station. The shelter will be an on-the-spot affair- the construction of which is determined by the equipment and material on hand plus your ingenuity, common sense, and ability to cooperate with personnel in other ratings. Before a Builder can get started on the shelter, you will have to furnish information, such as the number of generators to be sheltered, the dimensions of the generators, the method of running the generator load cables from the generator to the panelboard and from the panelboard to the feeder
![]() |
Typical 60-kW generator set.
system outside the building, and the arrangement of the exhaust system. Large generator units may have, connected or attached to them, engine equipment that requires extra space and working area. Included in this equipment are air-intake filters, silencers for air intake and exhaust, fuel and lubricating oil pumps, tanks, filters, and strainers. Also included are starting gear, isochronous regulating governors with over-speed trips, safety alarm and shutdown devices, gauges and thermometers, turning gear, along with platforms, stairs, and railings.
An even larger and more complete power plant may require separate equipment, such as a motor-driven starting air compressor and air storage tanks; motor-driven pumps for jacket water and lubricating oil cooling, or heat exchangers with raw cooling water pumps and lubricating oil coolers; and tanks that include day-fuel storage.
Be sure to provide enough working space around each unit for repairs or disassembly and for easy access to the generator control panels. Installation specifications are available in the manufacturer's instruction manual that accompanies each unit. Be sure to use them. Consulting with the Builder about these specifications may help cut installation costs and solve future problems affecting the shelter of the generator.
SERVICING THE GENERATOR
Before the set is operated, it must be serviced. We will use the 60-kW generator
set as an example for discussing the servicing of the set after you receive
it.
As you read this discussion, refer to figure for locating fill and drain points
and drain valves.
Batteries All 5-kW through 750-kW generator sets are furnished with dry-charged
batteries less the electrolyte. Battery electrolyte must be requisitioned separately.
You must be cautious when installing, activating, or maintaining batteries.
Before we discuss connecting WARNING Do not smoke or use an open flame in the
vicinity of batteries when servicing them. Batteries generate hydrogen a highly
explosive gas. When removing batteries, always remove both negative cables
before
removing the positive cables .
Battery electrolyte contains sulfuric acid and can cause severe burns. It is
highly toxic to the skin, eyes, and respiratory tract. Skin, eyes, and face
(chemical splash goggles, face shields) and respiratory protection are required.
Whenever electrolyte comes into contact with the body, the eyes, or the clothing,
you must rinse immediately with clean water, remove contaminated clothing,
and
then go to sickbay or the medical clinic for a thorough examination. The 60-kW
generator set is equipped with two 12- volt, 100-ampere-hour batteries. The
batteries are located under the radiator on aroll-out tray
. They are connected in series to supply 24 volts dc for starting
the generator set and operating direct current components. Two slave receptacles,
connected in parallel, permit easy connection to the batteries to
supply or obtain battery power. As we and servicing batteries, let's look at
a few safety points you must know about.
![]() |
Figure.- Battery cable connections and slave receptacles.
discuss activating the batteries,
refer to steps 1 through 3 (following) and figure
1.Open the battery compartment door and secure it to the radiator grille with
the door holder. SPECIFIC GRAVITY DESIRED USING 1.835 SPECIFIC USING 1.400 SPECIFIC
GRAVITY ACID GRAVITY ACID PARTS OF PARTS OF PARTS OFPARTS OF WATER A C I D WATER
ACID
2. Depress the button on top of the quick-release pins, lift up the pins, and
pull the roll-out tray assembly out.
3. Remove the filler caps. When you have electrolyte of the correct specific
gravity, do not dilute it, but fill the battery cells to the cell slots.
When you prepare your own electrolyte, consult a mixing chart (table). In this case, use the specific gravity value recommended in the instruction manual.
![]() |
Table.- Electrolyte Mixing
Chart
The temperature of the electrolyte when placed in the cells should be between
60° F and 90° F. IT SHOULD NEVER EXCEED 90° F.
A chemical reaction occurs when you add electrolyte to the battery, thereby
causing the battery to heat. Cool it artificially (cooling fans) or allow it
to stand at least 1 hour before placing it in service.
WARNING Be sure to add the acid to the water s-l-o-w-l-y, stirring constantly
and thoroughly.
![]() |
Figure.- Battery compartment.
You will notice at the end
of the cooling period that the level of the electrolyte has dropped because
of the electrolyte soaking into the plates and separators. Before placing the
battery in service, restore the electrolyte to its proper level. Remove any
electrolyte spilled on the battery, using a cloth dampened with a solution of
bicarbonate of soda and water.
Although you can place the battery in service 1 hour after filling it with electrolyte,
do so only in an emergency. If at all possible, give the battery an initial
light charge.
After the battery has been charged, connect the battery into the starting system
of the prime mover, as shown in figure. Always connect the negative cable
last.
4. Push in the roll-out tray assembly and install the quick-release pins .
Battery Charging
The manufacturer's manual may specify charging procedures for the type of battery
you are to charge. If so, follow those procedures.
There are several types of battery charges, but you will generally use a normal
charge, an equalizing charge, or a fast charge. We will discuss these three
types of charges briefly. For more information on storage or dry-cell batteries
and battery charging, refer to the Navy Electricity and Electronics Training
Series (NEETS), NAVEDTRA 172-01-00-88 (Module 1).
NORMAL CHARGE.- A normal charge is a routine charge that is given according
to the battery nameplate data during the ordinary cycle of operation to restore
the battery to its charged condition,
EQUALIZING CHARGE.- An equalizing charge is a special extended normal
charge that is given periodically to batteries as part of a maintenance routine.
It ensures that all the sulfate is driven from the plates and that all the cells
are restored to a condition of maximum specific gravity. The equalizing charge
is continued until the specific gravity of all cells, corrected for temperature,
shows no change for a 4-hour period.
FAST CHARGE.- A fast charge is used when a battery must be recharged
in the shortest possible time. The charge starts at a much higher rate than
is normally used for charging. It should be used only in an emergency, as this
type of charge may be harmful to the battery.
CHARGING RATE.- Normally, the charging rate of Navy storage batteries is given on the battery nameplate. If the available charging equipment does not have the desired charging rates, the nearest available rates should be used; however, the rate should never be so high that violent gassing occurs.
CHARGING TIME.- The charge must be continued until the battery is fully charged. Frequent readings of specific gravity should be taken during the charge and compared with the reading taken before the battery was placed on charge.
GASSING.- When a
battery is being charged, a portion of the energy breaks down the water in the
electrolyte. Hydrogen is released at the negative plates and oxygen at the positive
plates. These gases bubble up through the electrolyte and collect in the air
space at the top of the cell. If violent gassing occurs when the battery is
first placed on charge, the charging rate is too high. If the rate is not too
high, steady gassing develops as the charging proceeds, indicating that the
battery is nearing a fully charged condition.
WARNING A mixture of hydrogen and air can be dangerously explosive. No
smoking, electric sparks, or open flames should be permitted near charging batteries.
CHARGING PROCEDURE.-
If the instruction manual for the generator set is not available or if it does
not give the battery a charging procedure, proceed as follows: Connect the positive
battery charger terminal to the positive battery terminal and the negative charger
terminal to the negative battery terminal.
Charge the battery at a low rate (about 5 amperes) until the voltage and specific
gravity, corrected to 80° F (27° C) remains constant for at least 4
hours. If the temperature of the electrolyte reaches 110° F (43° C),
reduce the charging rate or stop the charge until the battery cools. NEVER PERMIT
THE TEMPERA-TURE TO EXCEED 115° F (46° C). During the charging, replenish
any water lost by evaporation.
Hydrometer A hydrometer is the instrument used to measure the amount of active
ingredients in the electrolyte of the battery. The hydrometer measures the SPECIFIC
GRAVITY of the electrolyte. Specific gravity is the ratio of the weight of the
electrolyte to the weight of the same volume of pure water, The active ingredient,
such as sulfuric acid or potassium hydroxide, is heavier than water. Because
the active ingredient is heavier than water, the more active the ingredient
in the electrolyte, the heavier the electrolyte will be; the heavier the electrolyte,
the higher the specific gravity.
A hydrometer is a glass syringe with a float inside it. The float is in a hollow,
glass tube, weighted at one end and sealed at both ends, with a scale calibrated
in specific gravity marked on the side. The electrolyte to be tested is drawn
into the hydrometer by the suction bulb. Enough electrolyte should be drawn
into the hydrometer so that the float will rise. Hydrometers should not be filled
to the extent that the float rises into the suction bulb. Since the weight of
the float is at its base, the float will rise to a point determined by the weight
of the electrolyte. If the electrolyte contains a large concentration of the
active ingredient, the float will rise higher than if the electrolyte has a
small concentration of the active ingredient.
To read the hydrometer, hold it in a vertical position and take the reading
at the level of the electrolyte. Refer to the manufacturer's technical manual
for battery specifications to find the correct specific gravity ranges. An example
of what your manual may say about the specific gravity is that for a fully charged
battery the specific gravity should be 1.280 ± 0.005. The manual may
tell you to recharge the battery if the specific gravity is less than 1.250.
Always return the electrolyte in the hydrometer to the cell of the battery from
which it was taken.
NOTE: Hydrometers should be flushed with fresh water after each use to
prevent inaccurate readings. Storage battery hydrometers must not be used for
any other purpose.
Perhaps it should be said
that adding the active ingredient (sulfuric acid, for example) to the electrolyte
of a discharged battery does not recharge the battery. Adding the active ingredient
only increases the specific gravity of the electrolyte and does not convert
the plates back to active material, and so does not bring the battery back to
a charged condition. A charging current must be passed through the battery to
recharge it.
Oil You must check the engine crankcase oil level before operating the generator
set. The engine dipstick is the crankcase oil level gauge. The dipstick in the
generator engine is the shielded type, which allows checking the oil level while
the engine is either stopped or running. The dipstick is stamped on both sides
to indicate the two different oil levels. The engine running side is stamped
as follows: "ADD," "FULL," and "RUNNING." The
engine stopped side is stamped as follows: "ADD," "FULL,"
and "STOPPED." Be sure to use the appropriate add and full marks,
depending on whether the engine is stopped or running. Also, ensure that the
appropriate side of the dipstick is up when inserting it since the underside
will be wiped in the gauge tube when the dipstick is removed, therefore, indicating
a false oil level reading.
To check the oil level,
first remove and wipe the oil from the dipstick. Loosen and remove the oil filler
cap (fig.) to allow the pressure to escape. Reinsert the dipstick (with the
appropriate side up) and remove it to observe the oil level. Add oil through
the fill tube, as required, to obtain the "full" level on the dipstick.
Be sure to use the proper grade of oil. A lubricant chart in the instruction
manual furnished with each generator will show the proper grade of oil to use
at the operating temperature.
Water Check that the level of coolant is within 2 inches (51 mm) of the top
of the radiator.
WARNING Do not attempt to remove the radiator cap until the radiator
has cooled to a point where there will be no built-up steam pressure. Failure
to observe this warning could result in second-or third-degree bums.
Using an antifreeze solution
tester, check that the antifreeze content is sufficient for the existing ambient
temperature. Add antifreeze as required.
Whenever you fill the radiator with coolant after it has been drained, fasten
a tag near the radiator cap. The tag should indicate the type of coolant and
the degree of protection the coolant gives.
Regardless of the air temperature, be sure to use an antifreeze solution in
the proportions recommended in the instruction manual for the generator.
Fuel The fuel tank should be filled with clean fuel oil, strained if necessary.
Service the fuel tank as follows:
WARNING Always maintain constant metal-to-metal contact between the fuel
tank filler neck and the spout of the fuel supply. That will prevent the possibility
of sparking caused by static electricity.
Remove the fuel tank filler
cap, and fill the fuel tank with the proper fuel. (Refer to the instruction
manual.) Replace the filler cap and wipe up any spilled fuel.
Remove the cap from the fuel tank drain valve and open the valve. Let water
and sediment drain into an approved nonflammable container. When clean fuel
runs out of the tank, close the drain valve and install the cap on the valve.
A day tank is one of the major components of the fuel system. It has a capacity
to permit engine operation for a minimum of 5 minutes. The day tank also provides
a settling point for contaminants (to prevent their entry into the engine) and
supplies fuel to the engine fuel pump.
The day tank contains a dual type of float switch. The upper float operates in conjunction with the fuel solenoid valve to maintain a predetermined fuel level in the tank. The lower float initiates an engine shut-down sequence. This sequence is initiated in the event that the fuel level in the tank will permit operation of the generator set at the rated load for only 1 minute. You must drain sediment and water from the day tank as you did from the fuel tank. Remove the cap from the day tank drain valve and open the valve. (Refer to fig. 3-1, view B, for the location of the tank and its drain valve.) Drain water and sediment into a container. Close the valve when clean fuel runs out of the tank, and install the cap back on the valve.
VENTILATION
WARNING Do not operate the generator set in an enclosed area unless
the exhaust gases are piped to the outside. Inhalation ofexhaust gases will
result in serious injury or death.
Keep the area around an operating generator set well ventilated at all times
so that the generator set will receive a maximum supply of air. Consider ventilation
when you install the units inside a building. Every internal combustionengine
is a HEAT engine. Although heat does the work, excess amounts of it must be
removed if the engine is to function properly. This can be accomplished by setting
the radiator grille of the engine near an opening in the wall and providing
another opening directly opposite the unit. In this manner, cool air can be
drawn in and the hot air directed in a straight line outdoors. These openings
can be shielded with adjustable louvers to prevent the entrance of rain or snow.
In addition, when the generator is operating in extremely cold weather, the
temperature in the room can be controlled by simply closing a portion of the
discharge opening. Additional doors or windows should be provided in the shelter
if the plants are installed in localities where the summer temperatures exceed
80° F at any time.
EXHAUST SYSTEM
The muffler and the exhaust pipe are connected to
the turbocharger exhaust elbow (fig. 34) and provide a path for engine exhaust
gases to exit the generator set. The muffler reduces the noise level of the
engine exhaust. The discharge opening of the muffler is covered by a hinged
cap to prevent water from entering the exhaust system when the generator is
not operating. Let's look at an example of an indoor installation. After bolting
the generator set to the concrete pad and enclosing it in a shelter, you are
about to vent the exhaust system to the outside. You lift the exhaust cap (fig.
3-4) and connect the gastight exhaust pipe to the discharge opening. You then
extend the pipe through the wall (or roof) of the building in a route that includes
no obstructions and a minimum number of bends. If you have arranged the pipe
to slope away from the engine, condensation will not drain back into the cylinders.
If the exhaust pipe has to be installed so that loops or traps are necessary,
place a drain cock at the lowest point of the system. All joints must be perfectly
tight; and where the exhaust pipe passes through the wall, you must take care
to prevent the discharged gas from returning along the outside of the pipe back
into the building. Exhaust piping inside the building must be covered with insulation
capable of withstanding a temperature of 1500° F.
![]() |
Figure.- Exhaust and breather system.
The crankcase breather tube is clamped to the engine breather assembly. The breather tube provides a path for engine crankcase vapors to exit the generator set. A rain shield is provided at the tube outlet to prevent rain from entering the tube when the generator is used outdoors.
GROUNDING
The generator
set must be connected to a suitable ground before operation.
WARNING Electrical faults in the generator set, load lines, or load equipment
can cause injury or electrocution from contact with an ungrounded generator.
The ground can be, in order of preference, an underground metallic water piping
system (fig., view A), a driven metal rod (fig.), or a buried metal plate (fig.).
A ground rod must have a minimum diameter of 5/ 8 inch (41 mm) if solid or 3/
4 inch (44 mm) if pipe. The rod must be driven to a minimum depth of 8 feet
(2.44 M). A ground plate must have a minimum area of 2 square feet (0.186 square
meter) and, where practical, be embedded below the permanent moisture level.
The ground lead must be at least No. 6 AWG (American Wire Gauge) copper wire. The lead must be bolted or clamped to the rod, plate, or piping system. Connect the other end of the ground lead to the generator set ground terminal stud (fig.). Use the following procedure to install ground rods:
1. Install the ground cable
into the slot in the ground stud and tighten the nut against the cable.
2. Connect a ground rod coupling to the rod and install the driving stud in
the coupling (fig.). Make sure that the driving stud is bottomed on the ground
rod.
3. Drive the ground rod into the ground until the coupling is just above the
ground surface.
4. Connect additional rod sections, as required, by removing the driving stud
from the coupling and installing another rod section in the coupling. Make sure
the new ground rod section is bottomed on the ground rod section previously
installed. Connect another coupling on the new section and again install the
driving stud.
![]() |
Figure - Methods of grounding generators.
![]() |
Figure - Grounding
procedure.
5. After the rod( s) have been driven into the ground, remove the driving stud and the top coupling. meet the requirements, they will be not less than 6 feet apart.
NOTE: The National Electrical Code(c) states that a single electrode consisting of a rod, pipe, or plate that does not have a resistance to ground of 25 ohms or less will be augmented by additional electrodes. Where multiple rod, pipe, or plate electrodes are installed to The resistance of a ground electrode is determined primarily by the earth surrounding the electrode. The diameter of the rod has only a negligible effect on the resistance of a ground. The resistance of the soil is dependent upon the moisture content. Electrodes should be long enough to penetrate a relatively permanent moisture level and should extend well below the frost line. Periodic earth resistance measurements should be made, preferably at times when the soil would be expected to have the least moisture.
You need to test the ground rod installation to be sure it meets the requirement for minimum earth resistance. The earth resistance tester may be used to perform the test. You should make this test before you connect the ground cable to the ground rod. When ground resistances are too high, they may be reduced by one of the following methods:
1. Using additional ground
rods is one of the best means of reducing the resistance to ground; for example,
the combined resistance of two rods properly spaced and connected in parallel
should be 60 percent of the resistance of one rod; the combined resistance of
three rods should be 40 percent of that of a single rod.
2. Longer rods are particularly effective where low-resistance soils are too
far below the surface to be reached with the ordinary length rods. The amount
of improvement from the additional length on the rods depends on the depth of
the low-resistance soils. Usually, a rather sharp decrease in the resistance
measurements is noticeable when the rod has been driven to a low-resistance
level.
3. Treating the soil around ground rods is a reliable and effective method for
reducing ground resistance and is particularly suitable for improving high-resistance
ground. The treatment method is advantageous where long rods are impractical
because of rock strata or other obstructions to deep driving. There are two
practical ways of accomplishing this result, as shown in figure . Where space
is limited, a length of tile pipe is sunk in the ground a few inches from the
ground rod and tilled to within 1 foot or so of the ground level with the treatment
chemical. The best treatment chemicals for all situations cannot be covered
within the scope of this manual. You may work with your engineering office to
determine the possible corrosive effect on the electrode. Examples of suitable
noncorrosive materials are magnesium sulfate, copper sulfate, and ordinary rock
salt. The least corrosive is magnesium sulfate, but rock salt is cheaper and
does the job.
The second method is applicable where a circular or semicircular trench
can be dug around the ground rod to hold the chemical (fig.). The chemical must
be kept several inches away from coming into direct contact with the ground
rod to avoid corrosion of the rod. if you wish to start the chemical action
promptly, you should go ahead and flood the treatment material. The first treatment
usually contains 50 to 100 pounds of material. The chemical will retain its
effectiveness for 2 to 3 years. Each replenishment of the chemical extends the
effectiveness for a longer period so that the necessity for future retreating
becomes less and less frequent.
![]() |
Figure - Methods of soil treatment for lowering of ground resistance.
4. A combination of methods
may be advantageous and necessary to provide desired ground resistance. A combination
of multiple rods and soil treatment is effective and has the advantages of both
of these methods; multiple long rods are effective where conditions permit this
type of installation.
After you are sure you have a good ground, connect the clamp and the ground
cable to the top ground rod section (fig. 3-6, view B), and secure the connection
by tightening the screw.
CONNECTIONS
A typical generator set is outlined in figure, showing the load cables and output
load terminals.
WARNING Before attempting to connect the load cables to the load terminals
of a generator set, make sure the set is not operating and there is no input
to the load.
Refer to figure as you follow this procedural discussion for making load connections.
1. Open the access door and disconnect the transparent cover by loosening six
quick-release fasteners. Remove the wrench clipped to the cover.
NOTE: Be sure to maintain the proper phase relationship between the cable
and the load terminals; that is, A0 to L1, B0 to L2, and so forth. 2. Attach
the load cables in the following order: L0, L3, L2, and L1 as specified in step
3 below.
![]() |
Figure- Load cable connections.
3. Insert the load cables
through the protective sleeve. Attach the cables to their respective load terminals,
one cable to each terminal, by inserting the cable in the terminal slot and
tightening the terminal nut with the wrench that was clipped to the transparent
cover. Install the wrench on the cover and install the cover.
4. Tighten the drawstring on the protective sleeve to prevent the entry of foreign
matter through the hole around the cable. You may convert the voltage at the
load terminals to 120/ 208 volts or 240/ 416 volts by properly positioning the
voltage change board (fig. 3-9). The board is located directly above the load
terminal board.
The procedure for positioning the voltage change board for the required output voltage is as follows:
1. Disconnect the transparent
cover by loosening the six quick-release fasteners.
2. Remove the 12 nuts from the board. Move the change board up or down to align
the change board arrow with the required voltage arrow. Tighten the 12 nuts
to secure the board.
3. Position and secure the transparent cover with the six quick-release fasteners
and close the access door.
PHASE SEQUENCE INDICATORS
The phase sequence indicator is a device used to compare the phase sequence
of three-phase generators or motors. Examples of its use are as follows: to
![]() |
Figure - Voltage change board.
compare the phase rotation
of an incoming alternator that is to be operated in parallel with an alternator
already on the line or to determine the phase rotation of motors being put into
use for the first time. One type of phase sequence indicator is a tiny three-phase
induction motor. The three leads of the motor are labeled "A," "B,"
and "C," as shown in figure 3-10. The insulating hoods over the clips
are of different colors: red for A, white for B, and blue for C. The rotor in
the instrument can be observed through the three ports as it turns so that you
can note the direction in which it rotates. The rotor can be started by means
of a momentary contact switch: it, stops again when you release the switch.
You also may use a solid-state phase sequence indicator with two lights. Whichever
light is on indicates the phase sequence of the voltage in the conductors that
the instrument is connected to; for example, the light labeled "ABC"
indicates one phase sequence, while the other light, labeled "BAC,"
indicates another. If you are working with three-phase conductors (all of the
same color) that are installed but not labeled, you may connect the phase sequence
indicator to the three conductors, turn on the power, check the phase sequence
of the conductors as connected to the instrument, and turn off the power. You
may then label the conductors with numbers, letters, or colored marking tape.
You also may check the phase sequence of an incoming alternator before paralleling
it with an operating load-side alternator. Connections must be made so that
the phase sequence of the two generators will be the same.
Figure shows the leads of two generators to be parallel. The proper procedure
for ensuring phase sequence with a phase sequence indicator is as follows: Connect
indicator terminals A to X1 , B to Yl , and C to Z1 , press the contact switch,
and note the direction of rotation of the rotor.
Now move the A terminal to X, the B to Y, and the C to Z, and again press the
switch. If the rotor turns in the same direction as before, the phase rotation
is the same for the alternators, and the connection can be made X to X1 , Y
to Y1 , and Z to Z1 . If the rotor turns in the opposite direction, transpose
the connections of any two of the incoming alternator leads before making the
connection. It is not absolutely necessary that A be connected to the left-hand
terminal, B to the center terminal, and C to the right-hand terminal. This is
a practical method, however, used to avoid the danger of confusing the leads.
The important thing is to ensure that the phase sequence indicator that was
used on X1 be brought down to X, the one used on Y1 to Y, and the one used on
Z1 to Z. Reversing any two of the leads will reverse the direction of rotation
of the rotor of the instrument.
Reference :
Website
http://www.tpub.com/engineering.htm
Back